PROJECTS

Adumoss has executed various electrical engineering projects as individually and with partnerships. Some selected projects demonstrating ADUMOSS’ expertise and capabilities are as follows:

CLIENT DESCRIPTION LOCATION STATUS
Ghana Rubber Estate Limited

EPC – GREL 1 Factory Local Power Substation Project

  • Electrical Design of the Grel 1 power substation
  • Procurement of MV and LV Switchgears
  • Procurement of 2 x 2MVA, 33kV/410V Transformer and 500kVA 410/33kV Transformers
  • Installation of 2 x 2MVA, 33kV/410V Transformer and 500kVA 410/33kV Transformer
  • Installation of MV and LV Switchgears
  • Laying and termination of MV, LV and Control Cables
  • Testing and Commissioning of the substation works
Apemanim Completed
AngloGold Ashanti Limited (Resettlement Project)

Power supply to new block 5 re-settlement project site

  • Installation of 11kV Medium voltage overhead lines
  • Installation of 415V low voltage overhead lines
  • Installation of 11k/0.433V pole mounted transformer
Tarkwa-Iduapriem Completed
Ghana Rubber Estate Limited

EPC – GREL 2 Factory 33KV Service Line Installation

  • Installation of 33kV Overhead Lines
  • Testing and Commissioning of the power Lines
Abura Completed
Electricity Company of Ghana

Injection of 200kVA, 11/0.433kV PMT and network improvement to relieve substation B120

  • Installation of 200KVA pole mounted Transformer c/w Earthing Layout system
  • Decommissioning of existing 50mm² AAL overhead lines
  • Laying of new 120mm² AAL overhead lines
Takoradi Completed
Ghana Rubber Estate Limited

EPC – GREL 2 Factory Warehouse Electrical Power Network Installation

Apemanim Completed
Jan De Nul Ghana Ltd

EPC - Electrical Installation for Office Facility

Takoradi Completed
Electricity Company of Ghana

Injection of 200Kva 33/0.433kV PMT to Relieve Substation G206 and Substation G181

  • Installation of 200KVA pole mounted Transformer c/w Earthing Layout system
  • Decommissioning of existing 50mm² AAL overhead lines
  • Laying of new 120mm² AAL overhead lines
Axim District Completed
PEEKOB

Warehouse Electrical Installation

Abura Completed
Ghana Rubber Estate Limited

Design & Integration of Automatic Transfer functionality into existing 33KV Switchgear

  • Electrical Design of Grel Tsibu Genset substation
  • Procurement of 5000A Synchronizing Panel
  • Procurement of 4MVA, 410V/33KV Transformer
  • Installation of 4MVA, 410KV/33KV Transformer
  • Installation of 5000A Synchronizing Panel
  • Laying and termination of MV, LV and Control Cables
  • Testing and Commissioning of the Genset substation works
Tsibu Completed
Electricity Company of Ghana

Network Improvement and Upgrade

Ngalekpoley Completed
Electricity Company of Ghana

Network Improvement and Upgrade

Eikwe, Axim District Completed
Ghana Rubber Estate Ltd.

Production floor cable works

Apemanim Completed
Electricity Company of Ghana (NEP)

National Electrification Project

  • Installation of 33KV overhead lines
  • Installation of LV Overhead Lines
  • Installation of 200KVA pole mounted Transformer c/w Earthing Layout system
Abura-Bando, Cape-Coast Completed
A.E.S.L, Accra

11-KV Power and Transformer connection to Ghana Railway Corp. Loco Running Shed.

Kumasi Completed
A&G Engineers & Consult.

11-KV OHL and Transformer Station to Ghana Rubber Estate Ltd.

  • Installation of 11kV overhead lines
  • Installation of 200KVA pole mounted Transformer c/w Earthing Layout system
Takoradi Completed
Electricity Company of Ghana

National Electrification Project

  • Installation of 33KV overhead lines
  • Installation of LV Overhead Lines
  • Installation of 200KVA pole mounted Transformer c/w Earthing Layout system
Abura-Bando, Cape-Coast Completed
Ghana Cocoa Board

EPC - Power and Transformer connection to Workshop Facility

Agona Swedru Completed
A.E.S.L, Accra

External & Internal Electrical Works to G.N.A Extension bloc

Accra Completed
Electricity Company of Ghana

National Electrification Project

  • Installation of 33KV overhead lines
  • Installation of LV Overhead Lines
  • Installation of 200KVA pole mounted Transformer c/w Earthing Layout system
Duakro, Cape- Coast Completed
Electricity Company of Ghana

National Electrification Project

  • Installation of 33KV overhead lines
  • Installation of LV Overhead Lines
  • Installation of 200KVA pole mounted Transformer c/w Earthing Layout system
Abakamu, Cape-Coast Completed
State Gold Mining Eng.

Electrical Installation to 3 Blocks of Flats for Gold Mining Corporation, Tarkwa

Tarkwa Completed
Electricity Company of Ghana (NEP)

National Electrification Project

  • Installation of 33KV overhead lines
  • Installation of LV Overhead Lines
  • Installation of 200KVA pole mounted Transformer c/w Earthing Layout system
Eture, Cape-Coast Completed
Estate Branch

Electrical Installation to Takoradi Beach Hotel

Takoradi Completed
Ghana Railway Corporation

EPC - Power and Transformer connection to Loco Running Shed

Kumasi Completed
Expro Group

Routine & Preventative Maintenance of 5 & 10-Ton Demag Overhead Cranes

New Amanful Completed
Cargill Ghana Ltd.

Installation of Demag 2ton Overhead Crane

Tema Completed
Ghana Rubber Estate Ltd.

2.5ton Demag Crane Installation

Apemanim Completed
Ghana Rubber Estate Ltd.

Demag Crane Extension / Maintenance

Apemanim Completed
Ghana Rubber Estate Ltd.

Installation of Demag 5ton Overhead Crane

Apemanim Completed
Contact Us